Hull || Project/Resources || Portfolio
Tontogany WWTP Lagoon Improvements
Village of Tontogany, Ohio
 |
| Lagoon Improvements |
Hull advanced a test pit trench within the
WWTP berm to observe the cause of a recently observed seep.
The test pit trench was backfilled with a bentonite-based
material (e.g., AquaBlok®) to provide a low-permeable
cut-off wall. This test pit approach allowed a geotechnical
exploration to be conducted and immediate improvements to
the berm to be implemented concurrently through maintenance
activities in lieu of an expensive berm reconstruction that
would possibly require an Ohio EPA permit modification.
To find out how Hull can help, please contact
Hull's Geoenvironmental Practice Leader, Shawn
McGee , PE at (440) 232-9945.
|